Work in rates: someone who takes a days does 1/a of the job each day.

Formulas and shortcuts

  • Together: 1/a + 1/b of the job a day, so they take ab/(a + b) days.
  • Pipes: a filling pipe adds 1/a a day, a leak subtracts 1/b: net time = ab/(b − a).
  • Partly done work: count the fraction done, then the fraction left.

Solved examples

  1. Asha can finish a project in 36 days and Ravi in 45 days. How many days will they take working together?

    • A. 9 days
    • B. 20 days
    • C. 40.5 days
    • D. 81 days

    Answer: B. 20 days

    • In one day they do 1/36 + 1/45 = 81/1620 of the work.
    • Together: 1620/81 = 20 days.
  2. Together, A and B finish a job in 12 days. A alone takes 21 days. How long would B take alone?

    • A. 24 days
    • B. 9 days
    • C. 33 days
    • D. 28 days

    Answer: D. 28 days

    • B's share of a day's work = 1/12 − 1/21.
    • B alone = (21 × 12) / (21 − 12) = 28 days.
  3. A pipe fills a tank in 12 hours; a leak empties the full tank in 20 hours. With both working, how long does the tank take to fill?

    • A. 30 hours
    • B. 32 hours
    • C. 7.5 hours
    • D. 8 hours

    Answer: A. 30 hours

    • Each hour: 1/12 − 1/20 = 8/240 of the tank.
    • Time = 240/8 = 30 hours.
  4. A can do a piece of work in 15 days. He works for 5 days and leaves; B finishes the rest in 12 days. How long would B take to do the whole work alone?

    • A. 12 days
    • B. 18 days
    • C. 36 days
    • D. 17 days

    Answer: B. 18 days

    • A did 5/15 of the work, so 10/15 was left.
    • B did 10/15 in 12 days, so the whole work takes 12 × 15/10 = 18 days.

Practise: 10 questions, 15 minutes

A new set every time, with every answer worked out at the end.

SectionQuestionsTime
Time and work, pipes1015 min

Every attempt is a new set of questions. No negative marking.