Formulas and shortcuts
- Together: 1/a + 1/b of the job a day, so they take ab/(a + b) days.
- Pipes: a filling pipe adds 1/a a day, a leak subtracts 1/b: net time = ab/(b − a).
- Partly done work: count the fraction done, then the fraction left.
Solved examples
Asha can finish a project in 36 days and Ravi in 45 days. How many days will they take working together?
- A. 9 days
- B. 20 days
- C. 40.5 days
- D. 81 days
Answer: B. 20 days
- In one day they do 1/36 + 1/45 = 81/1620 of the work.
- Together: 1620/81 = 20 days.
Together, A and B finish a job in 12 days. A alone takes 21 days. How long would B take alone?
- A. 24 days
- B. 9 days
- C. 33 days
- D. 28 days
Answer: D. 28 days
- B's share of a day's work = 1/12 − 1/21.
- B alone = (21 × 12) / (21 − 12) = 28 days.
A pipe fills a tank in 12 hours; a leak empties the full tank in 20 hours. With both working, how long does the tank take to fill?
- A. 30 hours
- B. 32 hours
- C. 7.5 hours
- D. 8 hours
Answer: A. 30 hours
- Each hour: 1/12 − 1/20 = 8/240 of the tank.
- Time = 240/8 = 30 hours.
A can do a piece of work in 15 days. He works for 5 days and leaves; B finishes the rest in 12 days. How long would B take to do the whole work alone?
- A. 12 days
- B. 18 days
- C. 36 days
- D. 17 days
Answer: B. 18 days
- A did 5/15 of the work, so 10/15 was left.
- B did 10/15 in 12 days, so the whole work takes 12 × 15/10 = 18 days.